Yuen Long Effluent Polishing Plant

Works Progress DC/2019/10

  November 2023
Main Site
Click each photo to see the corresponding works location

Construction of Utilities Corridor Englarge

Excavation and Lateral Support Works Englarge

Construction of Biogas Holder No.1 Englarge

Excavation and Lateral Support Works Englarge

Construction of CLP Substation and 11kV Switchgear House Englarge

Excavation and Lateral Support Works & Inlet Works (IW) Construction Englarge

Installation of Inclined Plate Settlers Englarge

Excavation and Lateral Support Works Englarge

Excavation and Lateral Support Works Englarge


October 2024

September 2024

August 2024

July 2024

June 2024

May 2024

April 2024

March 2024

February 2024

January 2024

+ 2023
+ 2022
+ 2021