Yuen Long Effluent Polishing Plant

Works Progress DC/2019/10

  July 2022
Main Site
Click each photo to see the corresponding works location

Driven H-piles Construction Englarge

Demolition Works for Existing Sludge Holding Tank Englarge

Construction of Temporary Administration Building (MIC Section) Englarge

Sheetpiling Works Englarge

Driven H-piles Construction Englarge

Temporary Diversion Works Englarge

Installation of Polymer Preparation and Dosing System Englarge

Installation of Ferric Chloride Dosing System Englarge