Yuen Long Effluent Polishing Plant

Works Progress DC/2019/10

  January 2023
Main Site
Click each photo to see the corresponding works location

Demolition of Existing Air Flotation Thickener Building Englarge

Sheetpiling Works Englarge

Sheetpiling Works Englarge

Construction of CLP Substation and 11kV Switchgear House Englarge

Primary Sedimentation Tanks (PST) Construction Englarge

Pipe Pile Wall Construction Englarge

Sheetpiling Works Englarge