The existing Yuen Long Sewage Treatment Works (YLSTW) serves Yuen Long Town, Yuen Long Industrial Estate and Kam Tin areas with a design capacity of 70,000 m3 per day. Our Project, namely "Yuen Long Effluent Polishing Plant" (YLEPP), is a construction project to increase the treatment capacity of YLSTW within the same footprint in two stages.

About

Main Works for Stage 1:

Contract No.: DC/2019/10

  • Commencement Date: 9 November 2020
  • Location: North of Yuen Long Industrial Estate, adjacent to Shan Pui River and Nam Sang Wai
  • Project Manager: AECOM Asia Company Limited
  • Main Contractor: Paul Y – CREC Joint Venture

Contract No.: DE/2020/01

  • Commencement Date: 13 June 2022
  • Location: North of Yuen Long Industrial Estate, adjacent to Shan Pui River and Nam Sang Wai
  • Project Manager: AECOM Asia Company Limited
  • Main Contractor: The Jardine Engineering Corporation Limited

Main Works for Stage 2:

Information for Stage 2 works are to be announced later.