Menu
|
繁
简
|
A
A
A
About the Project
Project Overview
Why is this construction
project needed?
Main Works
Benefits
What’s New
Works Progress
Sustainable Development
Architectural Design
Aerobic Granular
Sludge Technology
for Wastewater Treatment
Odour Control
BEAM Plus
Energy Efficiency
Energy Neutral
Environmental Issues
Community
Past Events
Newsletter
Community Liaison Group Meeting
Measures to fight COVID-19
Links
WORKS PROGRESS
Yuen Long Effluent Polishing Plant
Works Progress DC/2019/10
October 2021
Click each photo to see the corresponding works location
Demolition of Waste Storage Area
Temporary Water Heater House Construction
Temporary Sludge Holding Tank Construction
Driven H-piles construction
Demolition of the Existing Primary Sedimentation Tank
Temporary Diversion of Underground Utilities
Underground Utilities Diversion for Gravity Thickening Tank Construction
Demolition of the Final Sedimentation Tank
Removal of Sediment in Sludge Digestion Tank
Rectification Work for Gas Holder Examination
Replacement of Diffuser Membrane and other defective part in Aeration Tank
October 2024
September 2024
August 2024
July 2024
June 2024
May 2024
April 2024
March 2024
February 2024
January 2024
+
2023
December 2023
November 2023
October 2023
September 2023
August 2023
July 2023
June 2023
May 2023
April 2023
March 2023
February 2023
January 2023
+
2022
December 2022
November 2022
October 2022
September 2022
August 2022
July 2022
June 2022
May 2022
April 2022
March 2022
February 2022
January 2022
+
2021
December 2021
November 2021
October 2021
September 2021
August 2021
July 2021
June 2021
May 2021
April 2021
Back