Yuen Long Effluent Polishing Plant

Works Progress DC/2019/10

  July 2021
Main Site
Click each photo to see the corresponding works location

Temporary Diversion – Excavation and Lateral Support (ELS) Construction for Flowmeter Chamber Construction Englarge

Environmental Drill Holes Drilling Englarge

Predrilling Works Englarge

Driven H-piles construction Englarge

Demolition of existing Primary Sedimentation Tank Englarge

Replacement of Diffuser Membrane and other defective part in Aeration Tank Englarge

Removal of Sediment in Sludge Digestion Tank and Sludge Holding Englarge

Overhaul of existing facilities Englarge