Yuen Long Effluent Polishing Plant

Works Progress DC/2019/10

  October 2025
Main Site
Click each photo to see the corresponding works location

Sludge Thickening Building Construction Englarge

Driven H-piles Construction Englarge

Sludge Digesters Construction Englarge

Excavation and Lateral Support Works Englarge

Construction of Inlet Woks and Primary Treatment Facilities Englarge

Excavation and Lateral Support Works Englarge

Biological Treatment Facilities Construction Englarge

Tertiary Treatment Facilities Construction Englarge


January 2026

+ 2025
+ 2024
+ 2023
+ 2022
+ 2021