Yuen Long Effluent Polishing Plant

Works Progress DC/2019/10

  June 2021
Main Site
Click each photo to see the corresponding works location

Sheetpiling Works for Temporary Diversion Englarge

Construction of Temporary Covered Carpark Englarge

Temporary Administration Building Construction (Non-Modular in Construction Section) Englarge

Demolition of existing store Englarge

Driven H-piles construction Englarge

Installation of cameras for Eurasian Otter Survey Englarge

Demolition of existing Primary Sedimentation Tank Englarge

Predrilling Works Englarge

Replacement of Diffuser Membrane and other defective part in Aeration Tank Englarge

Removal of Sediment in Sludge Digestion Tank and Sludge Holding Englarge

Overhaul of existing facilities Englarge